Free method statement preparation worksheet and example

Gather the job scope, responsibilities, equipment, work phases and checks for a site-specific method statement.

Download free method statement worksheet (CSV)

Opens a free CSV in Excel or another spreadsheet. No registration required.

Preview the example method statementPreview the example method statement

Illustrative sample only. Not for site use.

View example method statement PDF

A planning aid, not an approved method statement or work instruction. A competent person must confirm the actual sequence, controls and required separate specialist plans before use.

Create your own method statement

Describe how your team will carry out a specific task in construction, cleaning, maintenance, manufacturing, warehousing or another workplace. HazardDocs uses guided job questions to prepare a method statement draft that you can check, edit and approve before PDF issue.

Start a method statement£14.99/monthView sample PDFs

Your job → editable AI draft → your review → PDF

A work sequence your team can use

A method statement connects preparation, delivery, access, execution, inspections and handover in a logical sequence. Explain the resources and supervision needed at each stage, the controls linked to your risk assessment and the points where work must wait for a check or authorisation. A list of general safety rules is less useful than a sequence that describes the actual job.

Example: installing equipment on an existing site

Your brief could describe delivery and unloading, movement to the work area, site preparation, installation, testing and handover. Identify interfaces with other contractors, agreed access restrictions and which checks belong to a specialist. The draft can organise this information, but it cannot confirm load capacities, engineering designs, isolation arrangements or conditions it has not inspected. Those details need verification by the people responsible.

How the method statement generator works

Create a job, select method statement and answer the relevant questions. Subscribe to generate the draft, edit it alongside your risk assessment and site rules, then record the competent reviewer before downloading.

What is included?

The £14.99 monthly subscription includes all supported documents, including the related risk assessment. A method statement does not replace required written arrangements or specialist plans. HazardDocs does not turn an unverified sequence into permission to start work.

Method statement template: a practical starting structure

Record the job scope and limits, people and responsibilities, equipment, agreed work sequence, relevant risk controls, points requiring confirmation or authorization, emergency arrangements and review details. An equipment installation example might have separate headings for delivery, preparation, installation, verification and handover. Fill in the real arrangements with the responsible people; this is a document structure, not a safe system of work.